Engineering Case Study

Level 2 Energy Audit of a Commercial Office Tower in Qatar – 24% Potential Electricity Savings

Conserve Solutions conducted a Level 2 energy audit of a commercial office tower in Doha, Qatar, identifying energy conservation measures with the potential to reduce annual electricity consumption by approximately 24%, with an estimated simple payback period of seven months.

Doha, Qatar | Energy Audit | CFD Analysis & Simulation

Conserve Solutions conducted a Level 2 energy audit of a commercial office tower in Doha, Qatar, identifying energy conservation measures with the potential to reduce annual electricity consumption by approximately 24%, with an estimated simple payback period of seven months. Doha, Qatar | Residential buildings | CFD Analysis & Simulation

Impact at a glance

24%Potential reduction in electricity consumption
QAR 741KEstimated annual cost savings
1,815 tCO₂ePotential annual carbon emission reduction
7 monthsEstimated investment payback

Client challenge

The client was incurring high operating costs due to substantial electricity and water consumption. Conserve Solutions was appointed to conduct a detailed energy audit, assess the performance of building systems and identify opportunities to reduce utility consumption and operating costs.

Financial and operational impact

In addition to high utility expenses, inefficient operation of building systems and unnecessary equipment operating hours can have further financial implications:

  • Higher electricity and water costs.
  • Increased operation and maintenance expenditure.
  • Increased equipment wear and potential reduction in equipment service life.
  • Potential premature capital expenditure on equipment replacement.

The audit aimed to identify the underlying causes of excessive consumption and recommend technically and financially feasible improvements.

Conserve’s approach

Conserve conducted a Level 2 energy audit covering the following activities:

  • Analysis of 33 months of historical electricity and water consumption data.
  • Review of building drawings, equipment details and operating schedules.
  • Establishment of an energy consumption baseline and performance benchmarks.
  • On-site assessment and evaluation of building systems and equipment performance.
  • Identification and technical evaluation of energy conservation measures (ECMs).
  • Estimation of energy savings, implementation costs, financial payback and associated carbon emission reductions.

The recommended measures were categorised into low-cost, medium-cost and capital-intensive improvements to help the client prioritise implementation based on technical feasibility, financial returns and available budgets.

Key findings and recommended improvements

The audit identified opportunities to improve the operating efficiency of HVAC equipment and chilled-water systems, particularly during periods of low occupancy and reduced cooling demand.

The principal recommendations included:

  • Optimisation of HVAC equipment operating schedules.
  • Improvement of chilled-water system performance.
  • Optimisation of chiller and pump sequencing.
  • Balancing of supply and exhaust airflow.
  • Improvement of Building Management System (BMS) control strategies.

Each recommended measure was evaluated for its potential energy savings, implementation cost and financial payback.

Projected energy, financial and environmental benefits

Performance indicators

QAR420,000

Estimated implementation cost

QAR740,946

Estimated annual cost savings

7months

Estimated simple payback period

Electricity

Baseline annual electricity consumption14.32GWh
Projected annual electricity consumption10.95GWh
Potential annual electricity savings3.37GWh
Potential electricity consumption reductionApprox.24%
1,815
tCO₂e

Estimated annual carbon emission reduction

The above savings are projections based on the energy audit findings and proposed conservation measures. Actual savings are subject to implementation and subsequent operating performance.

Project duration and deliverables

The energy audit was completed within eight weeks, including data collection, site assessment, engineering analysis and preparation of the final energy audit report.

The report provided the client with a prioritised list of energy conservation measures, estimated implementation costs, potential savings and financial payback periods to support investment and implementation decisions.